Outdoor Recreation Faciliites Inventory

 

Bayhorse Townsite, Beardsley and Pacific Mine Sites Environmental
Clean Up and Site Improvements Project:

                                         

Sealed Bids for the construction of the Bayhorse Townsite, Beardsley and Pacific Mine Sites Environmental Clean Up and Site Improvements located in Custer County, Idaho, was received April 10, 2008.  A Notice to Proceed has been issued issued to Dahle Construction, Salmon, Idaho.

Van Wyck RV Campground Project:

A Notice to Proceed has been issued to King Excavation, LLC, Caldwell, Idaho.  Construction Spring 2008.

Hells Gate Restroom Re-Roofs and Dworshak Restroom & Shelter Re-Roofs Projects:

Contract has been awarded to Granite Enterprises, Inc., Rathdrum, Idaho.   Notice to Proceed issued May 16, 2008.

Eagle Island Bridge, Eagle Island State Park:

A Notice to Proceed has been issued  to Concrete Placing Company, Boise, Idaho.

Scovell Center and Park Improvements - Harriman State Park Project: 

Following the Re-Bid, a Notice of Intent to Award has been issued to SE/Z Construction, LLC, Idaho Falls, Idaho.

Round Lake Central Sewer, Round Lake Potable Water and Round Lake Electrical Campground Upgrades Projects:

Bids were received a Notice of Intent to Award was issued August 6, 2008 to Buddy's Backhoe Service, Inc.

Farragut State Park Eagle Boat Launch Breakwater & Dock Replacement

Bids opened May 22, 2008.  Notice to Proceed issued to CE Kramer Crane & Contracting, Inc. Naples, Idaho.

Coeur d'Alene Parkway Higgens Point Dock Replacements

Notice to Proceed issued to Harrison Docks June 19, 2008.